Lead Time Calculator

Compare actual vs. quoted lead time order by order, and get a recommended safety buffer sized from your real variability.

Recommended safety buffer = 1.65 × standard deviation of actual lead time (a 95% service-level equivalent), rounded up.

Lead time calculator FAQ

Why does variability matter more than the average lead time?

A supplier who always takes 15 days is, in practice, easier to plan around than one who averages 10 days but sometimes takes 20 — even though the second one looks faster on paper. The safety buffer you need depends on how much the real lead time varies, not just its average, which is why this calculator focuses on standard deviation rather than the mean.

Worked example

If the quoted lead time is 10 days but your last few real orders took 9, 14, 8, 16, and 11 days (standard deviation ≈ 3.2 days), the recommended safety buffer = 1.65 × 3.2 ≈ 5.3 days, rounded to 6. You should plan around an effective 16-day lead time (10 quoted + 6 buffer), not the 10 days on the contract or purchase order.

How many orders do I need in my history for this to be reliable?

With fewer than 5-6 orders, the calculated standard deviation may not reflect the supplier's real behavior — a single one-off delay can distort the result. As a rule of thumb, once you have 10-15 orders the calculated buffer starts to stabilize; with less, treat it as a first estimate and refine it as you accumulate more history.

How do I use this safety buffer in my reorder point?

Add it to the quoted lead time before calculating your reorder point (using this site's reorder point or bulk reorder point calculator): use the quoted lead time plus this buffer as your "lead time" input, rather than the quoted lead time alone. That way your reorder point already accounts for the delays you actually see from that supplier, not just the ideal-case scenario.

A supplier's actual lead time is getting worse over time — what should I do?

If the trend shows "worsening," the buffer calculated from your full history may understate what you need going forward, because it's averaging older, more punctual orders together with the less reliable recent ones. In that case, recalculate using only your most recent orders (the last 3-6 months) so the buffer reflects the supplier's current behavior, not their full history.