Batch Size Calculator
Calculate the production batch size that minimizes setup (changeover) cost plus holding cost, for each product.
Formula per product: Batch size = √(2 × Annual demand × Setup cost ÷ Holding cost per unit per year).
Batch size FAQ
How is production batch size different from EOQ (economic order quantity)?
They use the same underlying formula (square root of 2 × annual demand × fixed cost ÷ holding cost), but they answer different questions. EOQ applies when you're buying from an outside supplier and the "fixed cost" is the cost of placing a purchase order. Batch size applies when you manufacture in-house and the "fixed cost" is the machine setup cost (changeover, adjustments, line downtime) each time you start a production run. If you buy finished goods, use the EOQ calculator; if you manufacture, use this one.
Worked example
You manufacture a product with annual demand of 12,000 units, a setup cost of €180 per changeover, and a holding cost of €3/unit/year. Batch size = √(2 × 12,000 × 180 ÷ 3) = √1,440,000 ≈ 1,200 units per run, which works out to about 10 runs a year (roughly one every 36 days).
How do I lower setup cost so I can run smaller batches?
This is the territory of SMED (single-minute exchange of die) techniques: standardizing tooling, prepping the next run while the current one is still producing, and splitting changeover tasks into "internal" (machine stopped) and "external" (machine running, can be done ahead of time). The lower you drive setup cost, the smaller the optimal batch gets — and smaller batches mean less tied-up capital and more flexibility to track real demand. There's more detail in this blog's article on SMED and production batch size.
What if the result gives me very few runs a year (huge batches)?
If the recommended batch size means producing only, say, 2-3 times a year, check whether the setup cost you entered is realistic — an inflated setup cost pushes the result toward bigger batches than you actually need. It can also mean it's genuinely worth investing in reducing that setup cost (SMED) instead of accepting batches that large with all the capital they tie up.
Is the optimal batch size always what I should actually produce?
It's a starting point, not a mandate. If you have warehouse capacity limits, product shelf-life constraints, or want to sync production with specific customer orders, adjust the result — the model assumes constant demand and unlimited storage space, which rarely holds exactly in practice.